Project Timeline
Autumn 2020
Commence preliminary environmental & technical assessments
Apply for grid connection
Autumn 2020 – Autumn 2021
Carry on with environmental and technical assessments
March 2021
Submit request for Pre-Application Advice
April 2021
Submit Screening Request and commence formal planning process
Commence consultation with local stakeholders
December 2021
Submit planning application
March 2023
Planning decision – approved with conditions
2024 (Indicative)
Discharge planning conditions
2024-2025 (Indicative)
Construction